Security of payment in Australia,
state by state

Every state and territory gives you a statutory right to be paid for construction work, and a fast adjudication process when you are not. The deadlines are short, they differ in every jurisdiction, and missing one usually means waiting for the next claim or losing the dispute by default. This hub compares all eight Acts and links to a full guide for each.

8 jurisdictions · updated July 2026 · not legal advice

What is security of payment?

Security of payment legislation gives anyone carrying out construction work, or supplying related goods and services, a statutory right to progress payments and a fast adjudication process to recover them. It operates alongside your contract and cannot be contracted out of.

Seven of the eight jurisdictions follow the East Coast model: you serve a payment claim, the respondent must answer with a payment schedule within a fixed number of business days, and if they schedule less than you claimed, or do not pay, you can take the dispute to a rapid adjudication. If the respondent misses the schedule deadline entirely, the claimed amount generally becomes a debt due in full. The Northern Territory uses the West Coast model instead: the Act implies payment terms into contracts that lack them, and either party can take a payment dispute to adjudication within a single window.

The catch is that every deadline is different in every state, and most of them are measured in business days that exclude different things. The table below compares the numbers that decide most disputes.

How do the deadlines compare across states?

Key statutory deadlines under each Act. Business days exclude weekends and public holidays plus each Act’s end-of-year shutdown: 27 to 31 December in NSW, SA, TAS and the ACT, but 22 December to 10 January in VIC, QLD and WA. The NT counts working days and shuts down 25 December to 7 January. Contracts can set shorter response periods where the Act allows it, so always read yours.

JurisdictionActPayment schedule duePayment due (default cap)Adjudication window
NSWBuilding and Construction Industry Security of Payment Act 1999 (NSW)10 business days after the claim, or earlier contract time (s 14(4))Head contractor 15 business days, subcontractor 20 (s 11(1A), (1B))10 or 20 business days depending on the trigger (s 17(3))
VICBuilding and Construction Industry Security of Payment Act 2002 (Vic)10 business days after the claim, or earlier contract time (s 15(4))Default 10 business days; terms beyond 20 business days have no effect (s 12(1), (1B))5 or 10 business days depending on the trigger (s 18(3))
QLDBuilding Industry Fairness (Security of Payment) Act 2017 (Qld)15 business days after the claim, or earlier contract time (s 76); not scheduling is an offenceDefault 10 business days (s 73); caps of 15 and 25 (QBCC Act ss 67W, 67U)20 or 30 business days depending on the trigger (s 79(2))
WABuilding and Construction Industry (Security of Payment) Act 2021 (WA)15 business days after the claim, or earlier contract time (s 25(1))Head contractor 20 business days, subcontractor 25; contract can only shorten (s 20)20 business days after you first become entitled to apply (s 28(4))
SABuilding and Construction Industry Security of Payment Act 2009 (SA)15 business days after the claim, or earlier contract time (s 14(4))15 business days after the claim if the contract is silent (s 11(1)(b))15 or 20 business days depending on the trigger (s 17(3))
TASBuilding and Construction Industry Security of Payment Act 2009 (Tas)10 business days after the claim; 20 for a homeowner respondent (s 19(3))Contract date, else tied to the s 19(3) schedule deadline (s 15(2))10 or 20 business days depending on the trigger (s 21)
ACTBuilding and Construction Industry (Security of Payment) Act 2009 (ACT)10 business days after the claim, or earlier contract time (s 16(4))Earlier of 15 business days after the claim and the contract date (s 13(1))10 or 20 business days depending on the trigger (s 19(3))
NTConstruction Contracts (Security of Payments) Act 2004 (NT)Notice of dispute within 10 working days if the contract is silent (Sch 1 cl 6)Within 20 working days if silent; terms over 30 working days read down (Sch 1 cl 6, s 13)65 working days after the payment dispute arises (s 28(1))

General information, not legal advice. Deadlines depend on your contract and the current Act, and amendments move them. Verify against the Act and your executed contract, or get advice, before relying on any date here.

Free tool

Turn a claim date into every deadline that runs from it

Pick your state, say whether you served or received the payment claim, and get the payment schedule, payment and adjudication deadlines computed business-day aware, each citing the section it comes from.

Open the deadline calculator

Frequently asked questions

Is security of payment the same in every Australian state?

No. Every state and territory has its own Act with different deadlines, and they are not interchangeable. Most follow the East Coast model of payment claims, payment schedules and adjudication, while the Northern Territory uses the West Coast model of implied contract terms and a single adjudication window. Always work from the Act where the construction work is carried out.

What happens if a respondent misses the payment schedule deadline?

In East Coast model states, a respondent who does not serve a payment schedule in time generally becomes liable for the full claimed amount as a statutory debt, which the claimant can recover in court or take to adjudication. It is one of the most expensive administrative misses in construction, which is why the response deadline matters more than almost any other date.

Can I contract out of security of payment legislation?

No. Every Australian security of payment Act voids contract provisions that attempt to exclude, modify or restrict the operation of the Act. Pay-when-paid provisions are also unenforceable in every jurisdiction. Your contract can give you more than the Act, but it cannot take away the statutory minimums.

General information, not legal advice. Deadlines depend on your contract and the current Act. Verify against the legislation for your state, or get advice, before relying on anything here.

Get started

The document intelligence platform your team needs.

Put every drawing, spec, contract and RFI to work — and let the monthly grind run itself.

A construction engineer reviewing drawings and a schedule from a site office overlooking live towers