How do I make a payment schedule under SOPA in Queensland?

Last reviewed July 5, 2026

Make a payment schedule by responding to a payment claim within 15 business days. Include details like the claimed amount, any amount you're willing to pay, and reasons for any deductions. Make sure it complies with the SOP Act requirements.

Key points

  • Respond within 15 business days.
  • Include claimed and payable amounts.
  • State reasons for any deductions.

When you get a payment claim, check it against the contract terms. You need to act quickly to avoid losing your right to dispute any amounts. Make sure your payment schedule is clear and follows the SOPA rules to protect yourself.