How do I make a payment schedule under SOPA in NSW?

Last reviewed July 5, 2026

Draft your payment schedule by outlining the work done, the claimed amount, and any reasons for withholding payment. Make sure to send it to the claimant within the specified timeframe, usually within 10 business days of receiving their payment claim.

Key points

  • Outline work done and claimed amount.
  • Include reasons for withholding payment if any.
  • Send schedule within 10 business days.

Follow the guidelines set out in the Security of Payment Act (SOPA) in NSW. Check the exact requirements as they can vary based on your project and contracts. Keep records of your communication and any documentation related to the claim for future reference.

How Alloovium helps

Alloovium can help by pulling relevant contract details and obligations, making it easier to draft accurate payment schedules.

See how it works

Related questions

General information for Australian construction professionals — not legal advice. Verify jurisdiction-specific requirements with the relevant regulator.